Following severe flooding at Woodberry Down Community Primary School in Hackney, a major refurbishment project was developed to restore and improve the school facilities.
Hackney Council committed approximately £1 million to the wider project, which included substantial drainage and building works alongside the replacement and upgrading of the school kitchen.
Nansen Green Limited was appointed by AtkinsRéalis, project managers for Hackney Council, to provide the specialist catering design for the new kitchen.
Our brief was to ensure that the new kitchen was not simply a replacement for the damaged facility, but a modern, efficient and practical catering environment designed around the needs of the school.
A complete commercial kitchen design
Nansen Green developed the proposed kitchen layout, catering equipment specification and detailed services requirements, working alongside the wider project team.
The new design included:
Three Rational iCombi Pro combination ovens
Commercial bratt pan and bulk cooking equipment
Walk-in chiller and walk-in freezer
Commercial pass-through dishwashers
Bespoke stainless-steel preparation areas
Improved dry storage and workflow
Mobile food service and clearing counters
The layout was developed around the complete catering operation, considering how food, staff, equipment and waste move through the kitchen.
Kitchen Design at Woodberry Down Primary School
Improving resilience and the working environment
The project also gave us the opportunity to address several important infrastructure considerations.
An automatic mechanical grease-management system was incorporated into the design to help reduce fats, oils and grease entering the drainage network and minimise the risk of future blockages.
The walk-in refrigeration was designed with the condensing units positioned externally rather than within the kitchen environment. This helps reduce excess heat within the kitchen and provides a more appropriate operating environment for the refrigeration plant.
The kitchen ventilation arrangements were also substantially upgraded, including improved extraction and fresh-air input. Heated make-up air was incorporated to help provide a more comfortable working environment during colder periods.
Coordinating equipment with the building
An important part of Nansen Green’s role was the production of a detailed catering services schedule.
This identified the gas, electrical, water, waste and drainage requirements for the new catering equipment, enabling these requirements to be coordinated with the wider mechanical and electrical works.
This stage is essential on refurbishment projects. A well-designed kitchen layout will only work if the building infrastructure has been properly planned to support the equipment.
By providing both the operational design and the technical equipment requirements, Nansen Green helped connect the needs of the catering service with those of the wider professional project team.
Specialist catering design for education
The Woodberry Down project demonstrates the breadth of Nansen Green’s catering design service.
Our support can include:
Commercial kitchen layouts
Catering equipment specification
Catering services schedules
Walk-in refrigeration
Ventilation and extraction requirements
Grease-management solutions
Warewashing design
Equipment budget development
Coordination with project managers, architects and M&E consultants
Installation and commissioning support
Our aim is to create practical, efficient and sustainable catering facilities designed around the needs of the school and the people who use them.
Planning a school kitchen project?
Whether you are considering an equipment upgrade, kitchen refurbishment or complete new catering facility, Nansen Green can provide independent specialist catering design and equipment consultancy from initial concept through to implementation.
We listen, find solutions and create sustainable improvements.